Commissioner & Director of Municipal Administration

Government of Telangana
CM/Minister Assurance Development Works
 

CM/Minister Assurance Development Works - CDMA

Physical Works Progress
ULB Armoor
Total Works 136
Administrative Sanction Amount (Rs.In Lakhs) 605.00
Pending
Estimation-Technical Sanction 136 0
Technical Sanction Given 135 1
Invitation of Tender 120 15
CR for Finalization of Agency 113 7
Work Order Issued 113 2
Work Started 37 76
Work Completed 34 3
Last Updated Date 25 Apr 2018





Financial Progress of Works
Administrative Sanctioned Amount(In Lakhs) 605
No.of Works called for Tender 0
Tendered Value(In Lakhs) 0
Amount Released(In Lakhs) 0