Physical Works Progress
ULB Bodhan
Total Works 79
Administrative Sanction Amount (Rs.In Lakhs) 1355.50
Pending
Estimation-Technical Sanction 40 39
Technical Sanction Given 0 79
Invitation of Tender 0 0
CR for Finalization of Agency 0 0
Work Order Issued 0 0
Work Started 0 0
Work Completed 0 0
Last Updated Date 14 Feb 2018





Financial Progress of Works
Administrative Sanctioned Amount(In Lakhs) 1355.5
No.of Works called for Tender 0
Tendered Value(In Lakhs) 0
Amount Released(In Lakhs) 0