Commissioner & Director of Municipal Administration

Government of Telangana
CM/Minister Assurance Development Works
 

CM/Minister Assurance Development Works - CDMA

Physical Works Progress
ULB Khammam Corp
Total Works 159
Administrative Sanction Amount (Rs.In Lakhs) 17716.64
Pending
Estimation-Technical Sanction 156 3
Technical Sanction Given 77 82
Invitation of Tender 75 2
CR for Finalization of Agency 62 9
Work Order Issued 62 1
Work Started 38 14
Work Completed 13 4
Last Updated Date 09 Jul 2018





Financial Progress of Works
Administrative Sanctioned Amount(In Lakhs) 19888.64
No.of Works called for Tender 10
Tendered Value(In Lakhs) 421.68
Amount Released(In Lakhs) 276.7413