Commissioner & Director of Municipal Administration

Government of Telangana
CM/Minister Assurance Development Works
 

CM/Minister Assurance Development Works - CDMA

Physical Works Progress
ULB Korutla
Total Works 13
Administrative Sanction Amount (Rs.In Lakhs) 300.00
Pending
Estimation-Technical Sanction 13 0
Technical Sanction Given 13 0
Invitation of Tender 13 0
CR for Finalization of Agency 13 0
Work Order Issued 13 0
Work Started 4 9
Work Completed 0 5
Last Updated Date 16 Jul 2018





Financial Progress of Works
Administrative Sanctioned Amount(In Lakhs) 300
No.of Works called for Tender 13
Tendered Value(In Lakhs) 278.78
Amount Released(In Lakhs) 0