SNoWORK_CODENAME_OF_THE_WORKADMIN_SANCTION_AMOUNTWORK_COMPLETION_DATEUPDATED_ON
11Pumping of water from Devadula Lift Irrigation Scheme to Dharmasagar157405/05/201619 Feb 2018
263Shifting of lines from siddhartha nagar to NIT in kazipet section D-1602-02-01-03-04-00211209/07/201726 Feb 2018
364Shifting of lines from waddepally x road to adalath circle subedari section D-1602-02-01-03-05-00250.36 20 Feb 2018
465Shifting of lines from adalath circle to ambedkar junction in nakkalagutta section D-1602-02-01-03-02-00415.65 20 Feb 2018
568Construction of Additional Vent to RUB existing at Shiva Nagar on 100 ft wide road from Warangal Head Post Office to Khammam Road 80003/07/201719 Feb 2018
669Providing Road Signages in the limits of GWMC4225/07/201719 Feb 2018
770Providing Road Signages in the limits of GWMC 24.1203/07/201719 Feb 2018
871LAYING OF BT ROAD FROM PATEL AND COMPANY SHOP (NIT PETROL PUMP) TO BANDAM TANK (STATIC TANK) AT DARGA ROAD, KAZIPET49.8712/06/201719 Feb 2018
972LAYING OF BT ROAD FROM EXISTING CULVERT AT CHURCH AT PRAKASH REDDYPETA TO VISHNUPRIYA GARDEN JN. ROAD ON 80-0" SHAYAMPET ROAD IN W.NO. 3244.5725/06/201720 Feb 2018
1073LAYING OF BT ROAD FROM GOVT. SCHOOL AT SHAYAMPET 80-0" TO VISHNUPRIYA GARDEN JN. ROAD39.6915/06/201720 Feb 2018
1174LAYING OF BT ROAD FROM CRS GARDEN TO TRIVI SCHOOL JN. AND GRAVEL ROAD FROM RAILWAY GATE SHAYAMPET 80-0" ROAD39.7910/02/201819 Feb 2018
1275LAYING OF BT ROAD FROM EXISTING BT ROAD TO 80-0" SHAYAMPET ROAD VIA VISHNUPRIYA GARDEN IN W.NO. 3828.112/02/201819 Feb 2018
1376LAYING OF BT ROAD FROM EXISTING BT ROAD FROM REVENUE COLONY TO JULAIWADA AUTO STAND JN. HANAMKONDA W.NO. 3718.310/02/201819 Feb 2018
1477Laying of SDBC layer from Sthambampally Junction to towards east fort upto Entrance with Gravel Shoulders on either side0.2210/02/201819 Feb 2018
1578Laying of SDBC layer from Vasanthapur Jn Dharmaram Railway Gate via Shambampally and Vanchagiri X road with gravel shoulders on either side 0.4210/02/201819 Feb 2018
1679Laying of SDBC layer from Venkatapur Jn. To existing PR BT road towards Venkatapur in GWMC limits with gravel shoulders on eighter side0.2903/05/201719 Feb 2018
1780Laying of SDBC layer from Shambunipet Jn. To Doopakunta X Road with gravel shoulders on either side0.3 20 Feb 2018
1881Laying of SDBC layer from Doopakunta X Road to Vasanthapur X road gravel shoulders on either side in GWMC0.2215/05/201719 Feb 2018
1982MANUFACTURE SUPPLY DELIVERY AND FIXING OF MS GRILLS IN DIVIDERS IN THE LIMITS OF GWMC - REACH - VII FROM NAIDU PETROL PUMP TO WEST FORT JUNCTION49.9415/06/201719 Feb 2018
2083MANUFACTURE SUPPLY DELIVERY AND FIXING OF MS GRILLS IN DIVIDERS IN THE LIMITS OF GWMC - REACH - V FROM MULUGU ROAD JUNCTION TO MGM JUNCTION33.506/07/201719 Feb 2018
2184MANUFACTURE SUPPLY DELIVERY AND FIXING OF MS GRILLS IN DIVIDERS IN THE LIMITS OF GWMC - REACH - IX FROM NATURE CURE HOSPITAL TO FLY OVER41.6503/05/201719 Feb 2018
2285MANUFACTURE SUPPLY, DELIVERY & FIXING OF MS GRILLS IN DIVIDERS IN THE LIMITS OF GWMC - REACH - I A)BEFORE KAZIPET JUNCTION (SHOPPING AREA) B) KAZIPET JUNCTION TO FATHIMANAGAR FLYOVER C)FATHIMANAGAR FLYOVER TO FATHIMA JUNCTION D) WADDEPALLY X ROAD TO COLLECTOR BUNGLOW E) COLLECTOR BUNGLOW TO DIG BUNGLOW48.504/05/201719 Feb 2018
2386MANUFACTURE SUPPLY DELIVERY AND FIXING OF MS GRILLS IN DIVIDERS IN THE LIMITS OF GWMC - REACH - II (FATHIMA JUNCTION TO WADDEPALLY X ROAD)49.9405/06/201719 Feb 2018
2487MANUFACTURE SUPPLY DELIVERY AND FIXING OF MS GRILLS IN DIVIDERS IN THE LIMITS OF GWMC - REACH - VIII FROM RAJ HOTEL TO NATURE CURE HOSPITAL41.6520/05/201720 Feb 2018
2588MANUFACTURE SUPPLY DELIVERY AND FIXING OF MS GRILLS IN DIVIDERS IN THE LIMITS OF GWMC - REACH - IV FROM DPO JUNCTION TO KUC X ROAD3930/04/201727 Feb 2018
2689MANUFACTURE SUPPLY DELIVERY AND FIXING OF MS GRILLS IN DIVIDERS IN THE LIMITS OF GWMC - REACH - III FROM KALOJI JN. TO AMBEDKAR JN., AMBEDKAR JN. TO DPO JN.29 05 Mar 2018
2790MANUFACTURE SUPPLY DELIVERY AND FIXING OF MS GRILLS IN DIVIDERS IN THE LIMITS OF GWMC - REACH - VI MGM TO GOPALASWAMY GUDI, GOPALASWAMY TEMPLE TO POCHAMMAMAIDAN, POCHAMMAMAIDAN TO KASHIBUGGA, KASHIBUGGA TO VENKATRAMA JN.49.9418/05/201726 Feb 2018
2891CENTRAL MEDIANS 18 No. of works takenup by KUDA Rs. 6.73 Crores67310/05/201705 Mar 2018
29115Avenue Plantation (1 Work)12.7117/01/201809 Mar 2018
30117Translocation of Trees27.5 09 Mar 2018
31119Development of Grave Yard in Shiva Nagar186 09 Mar 2018
32134Providing Physical facilities in Government Schools of GWMC area 2144 20 Feb 2018
33135Procurement of 12Ltr Capacity house hold garbage collection bins for segregation of Waste 389 20 Feb 2018